Which of the following are the primary objectives of risk monitoring in software project tracking?P: To assess whether predicted risks do, in fact, occurQ: To ensure that risk aversion steps defined for the risk are being properly appliedR: To collect information that can be used for future risk analysis(A)Only P and Q(B)Only P and R(C)Only Q and R(D)All of P, Q, R |