Which Of The Following Defines The Total Scope Of The Project And Represents The Work Specified In The Current Approved Project Scope Statement? |
|
Answer» The WBS is a hierarchical decomposition of the work to be PERFORMED by the PROJECT team. It defines the TOTAL scope of the project. It represents the work specified in the currently APPROVED project scope statement. The WBS is a hierarchical decomposition of the work to be performed by the project team. It defines the total scope of the project. It represents the work specified in the currently approved project scope statement. |
|