Which Of The Following Is A Hierarchical Representation Of Project Risks?

Answer»

The RISK Breakdown Structure (RBS) is a hierarchical presentation of the project risks SORTED by risk CATEGORIES.

The Risk Breakdown Structure (RBS) is a hierarchical presentation of the project risks sorted by risk categories.