Which Of The Following Is Not A Project Competing Constraint? |
|
Answer» Six competing project constraints are scope, QUALITY, SCHEDULE, BUDGET, resources and RISK. Procurement is not a project competing constraint. Six competing project constraints are scope, quality, schedule, budget, resources and risk. Procurement is not a project competing constraint. |
|