Which of the following relation is correct for design of channel/I-section purlin?(a) (Mz/Mdz) + (My/Mdy) ≥ 1(b) (Mz/Mdz) + (My/Mdy) ≤ 1(c) (Mdz/Mz) + (My/Mdy) ≤ 1(d) (Mdz/Mz) + (Mdy/My) ≥ 1The question was posed to me during a job interview.The question is from Purlins topic in portion Design of Beams of Design of Steel Structures |
|
Answer» Correct option is (b) (Mz/Mdz) + (My/Mdy) ≤ 1 |
|