Which Of These Precedence Relationships Is Most Commonly Used In The Precedence Diagramming Method?

Answer»

Finish-to-START relationships indicate that the NEXT task is not ABLE to start until the ONE preceding it is completed. This is the most commonly used type of activity relationship.

Finish-to-Start relationships indicate that the next task is not able to start until the one preceding it is completed. This is the most commonly used type of activity relationship.