Which Of These Processes Is Not A Project Time Management Process?

Answer»

Create WBS is a PROCESS in the Project SCOPE MANAGEMENT area. The other options are all Project TIME Management PROCESSES.

Create WBS is a process in the Project Scope Management area. The other options are all Project Time Management processes.