InterviewSolution
Saved Bookmarks
| 1. |
Which Of These Processes Is Not A Project Time Management Process? |
|
Answer» Create WBS is a PROCESS in the Project SCOPE MANAGEMENT area. The other options are all Project TIME Management PROCESSES. Create WBS is a process in the Project Scope Management area. The other options are all Project Time Management processes. |
|