| 1. |
Which Of These Types Of Precedence Relationships Is Least Commonly Used In The Precedence Diagramming Method? |
|
Answer» Start to Finish relationships INDICATE that the next task cannot be completed until the one PRECEDING it has STARTED. This type is not COMMONLY used. Start to Finish relationships indicate that the next task cannot be completed until the one preceding it has started. This type is not commonly used. |
|