Who decides the Duration (length) of Sprint? |
|
Answer» The Scrum team. The scrum team which INCLUDES PO, Scrum Master, and the development team decides the sprint LENGTH. The team during retrospective will inspect and adapt on the sprint length and arrive at an agreement. The scrum master acts as a facilitator to help the team arrive at an agreement and he/she will COME in only when the team is UNABLE to decide and helps to set the sprint length. Once decided, the duration of sprint usually remains the same throughout the PROJECT. |
|