Who has the authority to cancel a Sprint?

Answer»

Product OWNER.The Sprint can be called off before ending up the Sprint time-box. Only the Product Owner has the authority to cancel a Sprint. This happens when the Product Owner realizes that it makes no sense to FINISH the Sprint, as defined in Sprint Backlog. The PO may cancel the sprint under the influence of any Stakeholder, the DEVELOPMENT team, or the Scrum MASTER.