1.

If TL is the largest allowable event occurrence time, total activity slack (s) is equal to

Answer»

 All of the above



If TL is the largest ALLOWABLE EVENT OCCURRENCE time, TOTAL activity slack (s) is equal to
- Latest start time earliest start time
- Latest FINISH time earliest finish time (EFT)
- TLEFT

2.

Tick the odd man out

Answer»

 Galileo



Galileo DISCOVERED TELESCOPE, but also a series of devices that would have a profound impact on surveying, the use of artillery, the development of clocks, and meteorology

3.

When slack of an activity is positive

Answer»

 It represents a situation where extra resources are available and the completion of project is not delayed



When SLACK of an ACTIVITY is POSITIVE - it represents a situation where extra resources are available and the completion of the project is not delayed.
When slack of an activity is negative- it represents that a program falls behind schedule and additional resources are REQUIRED to complete the project in time.
When slack of an activity is zero - the activity is CRITICAL and any delay in its performance will delay the completion of the whole project.

4.

When slack of an activity is negative

Answer»

 It REPRESENTS that a PROGRAMME falls behind schedule and additional resources are REQUIRED to complete the project in time



When SLACK of an ACTIVITY is negative It represents that a programme falls behind schedule and additional resources are required to complete the project in time