12 men complete a work in 9 days. After they have worked for 6 days, 6 more men join them. How many days will they take to complete the remaining work? |
|
Answer» 2 days 12 men's 6 day's work = 1/9 * 6 = 2/3 Remaining work = 1 - 2/3 = 1/3 18 men's 1 day work = 1/108 * 18 = 1/6 1/6 work is done by them in 1 day. 1/3 work is done by them in 6 * 1/3 = 2 days. |
|