A completed his office project in 52 days. B is 30% more efficient than A. How many days will B take to complete the same project?1. 402. 253. 654. 13 |
|
Answer» Correct Answer - Option 1 : 40 Given: A can complete his office project in 52days B is 30% more efficient than A. Formula Used Work = Time×Efficiency Time is inversely proportional to Efficiency. Calculation Let the days taken by Bto complete the project bex According to the question, The ratio of efficiency of B and A = 130 : 100 The ratio of time taken byBandA= 100: 130 = 10: 13 The time taken by B to complete the project = (52) × (10/13) ⇒ x = (52) × (10/13) ⇒x = 40 ∴ Bwill take 40days to complete the project. |
|