1.

45 men working 5 hours per day finish a piece of work in 12 days. In how many days can 60 women working 4 hours per day finish the same piece of work? 2 women do as much work in one hour as 1 man does

Answer»

15 days



E1E2 = 2 x 1, 1 x 15 = 21.5 x 4 x 3
w = w
Because M1 D1 T1 H1 W2 = M D2 T2 B2 W1
D4 = 45x12x5x4/60x4x3 = 15 days