8 Man Work For 6 Days To Complete A Work. How Many Men Are Required To Complete Same Work In 1/2 Day?

Answer»

To complete a work for 6 days, 8 men require

For complete a work for 1 day = 6*8 = 48 men

For complete a work in HALF a day(1/2) = 48*2 = 96 men.

To complete a work for 6 days, 8 men require

For complete a work for 1 day = 6*8 = 48 men

For complete a work in half a day(1/2) = 48*2 = 96 men.