| 1. |
A alone can complete a work in 16 days and B alone can complete in 12 days. Starting with A they work on alternate days. The total work will be completed in? |
|
Answer» 13 ¾ (A+B)’s 2 DAY work = 1/16 + 1/12 = 7/18 |
|