1.

A contractor decided to build a bridge in 35 days. He employed 60 men in the beginning and 40 more after 17 days and completed the work on time. If he had not employed the additional men, how many day

Answer»

13 DAYS



Let 60 men COMPLETE the work in x days
 60 men