B and C work together can complete work in 8 days A and B together can complete same work in 12 days and A& C together complete in 16 days in total how many days A,B and C complete the same work toge |
|
Answer» 7 5/13 (A+B+C)’s 2 day WORK = (1/8+1/12+1/16 ) = 13/48 |
|