1.

Concrete is filled in how many layers in slump cone in slump test.(a) 3(b) 2(c) 6(d) 4I got this question in a national level competition.My query is from Tests on Concrete in section Building Construction of Basic Civil Engineering

Answer»

Right CHOICE is (d) 4

For explanation I WOULD say: The fresh concrete is filled in slump cone in 4 layers. Each layer is tamped 25 times with a 16MM pointed rod. The SPECIFICATIONS are given in IS 1199.