PSC stands for:(a) Post-Stressed Concrete(b) Post-Strained Concrete(c) Pre-Stressed Concrete(d) Pre-strained ConcreteThis question was posed to me in exam.This interesting question is from RCC, PSC and Ferro-Cement topic in chapter Building Construction of Basic Civil Engineering

Answer»

The CORRECT answer is (c) Pre-Stressed CONCRETE

Explanation: Pre-Stressed Concrete REFERS to the block of concrete which has been subjected to compression prior to SUPPORTING any LOADS.