1.

The result of Vee-Bee test is expressed in terms of:(a) s(b) m(c) N/mm^2(d) kgI got this question in an online interview.This intriguing question comes from Tests on Concrete topic in portion Building Construction of Basic Civil Engineering

Answer»

Right answer is (a) s

For explanation: The time is TESTED is Vee-Bee test. Time REQUIRED to complete remoulding of CONCRETE when SUBJECTED to the vibration is measured. It is then expressed in seconds.