1.

Determine the pondage factor if the plant is working at time of 8 hrs?(a) 2.5(b) 3.8(c) 1(d) 3I got this question at a job interview.I need to ask this question from Hydrographs in portion Hydro Electric Power Plant of Energy Engineering

Answer»

Correct option is (d) 3

The best explanation: Pondage factor = T1/T2

= (Total NUMBER of hours in one day)/(Total number of hours PLANT is running)

P.F = 24/8= 3.