Determine the pondage factor if the plant is working at peak time of 16 hrs?(a) 1.5(b) 0.75(c) 2.5(d) 0.3I have been asked this question in an online quiz.The query is from Hydrographs in chapter Hydro Electric Power Plant of Energy Engineering

Answer»

Right ANSWER is (a) 1.5

To ELABORATE: Pondage factor = T1/T2 = (Total number of HOURS in ONE day)/(Total number of hours PLANT is running)

P.F = 24/16= 1.5.