1.

How Can We Set The Options For Capacity Reports Cm01?

Answer»

This will possible depend on your config, but the options I use are: 

  • Settings>GENERAL>
  • Tick, Cumulation of reqmts, Dyn. capacity cumul. and then select the hierarchy you have set up. 
  • I then select the financial year (as we are budget driven) using Entry type A and the start/finish of the financial year. 
  • I select period Month. 
  • Then click tick. 
  • I then select the WORK centre I require. or arm of the hierarchy. 
  • You can then select STANDARD overview and also select graphs or if you NEED a DETAILED list press that button.

This will possible depend on your config, but the options I use are: 