Is There Any Way By Which We Can Lock Two Specific Wbs Elements Say Overheads And Other Expenses, So That The User Cannot Release Pr?

Answer»

The easiest way would be to define the project release process in the bottom-up fashion. That means, you will only release the activities/WBS ELEMENTS that you need from TIME to time during the COURSE of the project. That way, charges won't be accrued on a WBS element until it's released (so, don't release it until it's ready for collecting COSTS).

The easiest way would be to define the project release process in the bottom-up fashion. That means, you will only release the activities/WBS elements that you need from time to time during the course of the project. That way, charges won't be accrued on a WBS element until it's released (so, don't release it until it's ready for collecting costs).