In a load flow problem solved by Newton-Raphson method with polar coordinates, the size of the Jacobian is 100×100. If there are 20 PV buses in addition to PQ buses and a slack bus, the total number of buses in the system is 61 |
Answer» In a load flow problem solved by Newton-Raphson method with polar coordinates, the size of the Jacobian is 100×100. If there are 20 PV buses in addition to PQ buses and a slack bus, the total number of buses in the system is
|
|