In which stage of process improvement bottlenecks and weaknesses are identified?(a) Process measurement(b) Process analysis(c) Process change(d) None of the mentionedThe question was posed to me in an online interview.My question is taken from Process Improvement topic in division Software Maintenance of Software Engineering

Answer» CORRECT CHOICE is (b) Process ANALYSIS

Explanation: In Process analysis the current process is assessed and BOTTLENECKS and weaknesses are identified.