Is There Any Way By Which We Can Lock Two Specific Webs Elements Say Overheads And Other Expenses, So That The User Cannot Release Pr? |
|
Answer» The EASIEST WAY would be to DEFINE the project RELEASE process in the bottom-up fashion. That means, you will only release the activities/WBS elements that you need from time to time during the course of the project. That way, CHARGES won’t be accrued on a WBS element until it’s released (so, don’t release it until it’s ready for collecting costs). The easiest way would be to define the project release process in the bottom-up fashion. That means, you will only release the activities/WBS elements that you need from time to time during the course of the project. That way, charges won’t be accrued on a WBS element until it’s released (so, don’t release it until it’s ready for collecting costs). |
|