Kim can do a work in 3 days while David can do the same work in 2 days. Both of them finish the work together and get Rs. 150. What is the share of Kim? |
|
Answer» Kim's wages : DAVID's wages = Kim's 1 day work : David's 1 day work = 1/3 : 1/2 = 2:3 |
|