P can complete work in 12 days working 8 hrs a day. Q can complete the same work in 8 days working10 hrs a day. If both P and Q working 8 hrs a day in how many days can they complete the work?

Answer»

5 5/11



P can COMPLETE WORK in 12 X 8 = 96 hrs