P is three times as fast as Q and working together, they can complete a work in 12 days. In how many days can Q alone complete the work?

Answer»

16 DAYS



P = 3Q

P + Q = 3Q + Q = 4Q

These 4Q PEOPLE can do the work in 12 days, which means Q can do the work in 48 days.

Hence, P can do the work in 16 days.