Rohan can paint 1/3 of a painting in 6 days. How many days will he take to complete painting?

Answer»

The given details are,

Number of days taken by Rohan for painting 1/3 of painting is 6 days

Number of days taken by Rohan to complete the painting = 6/(1/3)

= 6 × 3 = 18

∴ Rohan can complete painting in 18 days.