Sixty men can stitch 200 shirts in 30 days working 8 hours a day. In how many days can 45 men stitch 300 shirts working 6 hours a day? |
|
Answer» 80 We have M1 D1 H1 / W1 = M2 D2 H2 / W2 (VARIATION rule) (60 * 30 * 8)/ 200 = (45 * D2 * 6) / 300 D2 = (60 * 30 * 8 * 300) / (200 * 45 * 6)=> D2 = 80. |
|