| 1. |
Three workers working all days can do a work in 10 days. But one of them having other employment can work only half time. In how many days the work can be finished? |
|
Answer» 12 days Sum of each PERSONS’ ONE day’s work = 1/3 ×10 + 1/3 ×10 + 1/3× 20 = 1/30 + 1/30 + 1/60 |
|