1.

What is a tangible output of an activity that is predicted in a project plan?(a) Deliverable(b) Activity(c) Condition(d) ProcessI got this question in my homework.I want to ask this question from Process Improvement in division Software Maintenance of Software Engineering

Answer» CORRECT OPTION is (a) Deliverable

Explanation: NONE.