Why are the user stories not estimated in man hours? |
|
Answer» One of the most common approaches for evaluating teamwork is to estimate in man-hours. While man-hours are SIMPLE to comprehend, they have a number of SIGNIFICANT drawbacks:
The benefits of estimating USER STORIES in points include the following: There is no association between the estimator's skills and experience, and story points are independent of the story's author. The team members can estimate more correctly since story points are a measurement of relative sizes, and the size of the story cannot be changed by external forces. As team behavior takes precedence over individual conduct, Story Points encourages collaboration. The team comes together when they use planning poker to estimate story points. As teams exchange, constructively criticize, argue, and have fun playing poker cards to arrive at an agreement on estimations, it serves as a team-building activity. |
|