Explore topic-wise InterviewSolutions in .

This section includes InterviewSolutions, each offering curated multiple-choice questions to sharpen your knowledge and support exam preparation. Choose a topic below to get started.

1.

The most widely used expression for the growth rate of micro-organisms is given by Monod:(a) Total rate of microbial growth,(b) True(c) FalseI had been asked this question in class test.This key question is from Principle for the Preparation of Water Supply in portion Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

The correct ANSWER is (a) TOTAL rate of microbial growth,

The BEST I can explain: Biomass Growth Rate

The most widely USED expression for the growth rate of micro organisms is given by Monod:

Total rate of microbial growth,

where,

mm = maximum specific growth rate

X = micro organism CONCENTRATION

S = substrate concentration

Ks = substrate concentration at one half the maximum growth rate

Similarly, rate of substrate utilization,

dS = k X S

dtKs+ S

where,

k = maximum specific substrate utilization rate.

2.

Cracking of the concrete section is nearly impossible to prevent.(a) True(b) FalseI have been asked this question at a job interview.I'd like to ask this question from Structural Designing and Thumb Rules topic in portion Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Right choice is (a) True

To explain I would say: However, the size and LOCATION of CRACKS can be limited and controlled by appropriate reinforcement, control joints, CURING methodology and concrete mix design. Cracking can ALLOW moisture to penetrate and corrode the reinforcement. This is a serviceability failure in limit state design. Cracking is normally the result of an inadequate quantity of rebar, or rebar spaced at too great a distance. The concrete then cracks either under excess loading, or due to internal effects such as early thermal shrinkage while it cures.

Ultimate failure leading to collapse can be caused by crushing the concrete, which OCCURS when compressive stresses exceed its strength, by yielding or failure of the rebar when bending or shear stresses exceed the strength of the reinforcement, or by bond failure between the concrete and the rebar.

3.

For initial estimate for a beam design, the width is assumed?(a) 1/10th of span(b) 1/30th of span(c) 1/15th of span(d) 1/5th of spanI had been asked this question in final exam.My question is taken from Structural Designing and Thumb Rules in portion Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

The correct option is (b) 1/30th of span

The explanation: Design CODES prescribe beam width limitations to minimise the shear lag effect on the formation of full-width plastic hinges and achieving the EXPECTED capacity. However, owing to insufficient experimental and analytical studies, empirical design formulas for the beam width limitation, with remarkably different results, have been implemented in different design codes. In this PAPER, parametric studies of the influence of key parameters on the behaviour of wide beam–column connections are conducted BASED on available test results. An effective beam-width MODEL is analytically developed using the equivalent-frame representation, where the effects of torsion of transverse beams and flexure around the joint core are considered. The validity of the model is verified using flexural strengths of test specimens, covering a wide range of design parameters.

4.

A foundation rests on __________(a) base of the foundation(b) foundation soil(c) subgrade(d) foundation soil and subgradeThis question was addressed to me during an internship interview.My question is based upon Structural Designing and Thumb Rules in portion Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Right option is (d) foundation soil and subgrade

Easiest EXPLANATION: A foundation (or, more commonly, base) is the element of an architectural structure which connects it to the ground, and transfers loads from the structure to the ground. FOUNDATIONS are generally considered either SHALLOW or deep. Foundation ENGINEERING is the application of soil mechanics and rock mechanics (Geotechnical engineering) in the design of foundation elements of STRUCTURES.

5.

_____________ is the technique of estimating or determining the fair price or value of a property such as a building, a factory, other engineering structures of various types.(a) depreciation(b) capital value(c) valuation(d) taxationThe question was asked in an international level competition.This is a very interesting question from Values, Tax, Funds & Rents etc topic in section Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Right option is (c) valuation

For explanation: By valuation the present value of a property is determined. The present value of property MAY be decided by its SELLING price, or INCOME or rent it may fetch. The value of property depends on its structure, life, MAINTENANCE, location, bank interest, LEGAL control, etc. The value also depends on supply on demand and the purpose for which valuation is required.

6.

The maximum area of tension reinforcement in beams shall not exceed?(a) 1.5%(b) 4%(c) 7%(d) 0.5%I have been asked this question in an interview.I would like to ask this question from Structural Designing and Thumb Rules in section Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Correct answer is (B) 4%

For explanation: If tensile reinforcement of beam should EXCEED 4% of total gross area then some CRACK will be developed in concrete.

7.

A power canal refers to a canal used for hydraulic power generation, rather than for transport.(a) True(b) FalseI got this question during an internship interview.The question is from Reports on Estimate for the Construction of Road and Irrigation Channel in portion Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer» RIGHT answer is (a) True

Best explanation: Nowadays power canals are built almost exclusively as PARTS of hydroelectric power stations. Parts of the United STATES, particularly in the Northeast, had enough fast-flowing rivers that water power was the primary means of powering factories (usually textile mills) until after the American Civil War. For example, Lowell, Massachusetts, CONSIDERED to be “The Cradle of the American Industrial Revolution,” has 6 miles (9.7 km) of canals, built from around 1790 to 1850, that PROVIDED water power and a means of transportation for the city. The output of the system is estimated at 10,000 horsepower.
8.

The kind of canal section involved in irrigation work is __________(a) canal high in embankment in partly in excavation(b) canal partly in excavation and partly in embankment(c) canal less in embankment(d) canal half in excavationI got this question in my homework.Question is taken from Reports on Estimate for the Construction of Road and Irrigation Channel topic in portion Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer» RIGHT answer is (b) canal partly in excavation and partly in embankment

Explanation: There are generally three kinds of canal sections INVOLVED in irrigation works and they are:-

• Canal fully in excavation

• Canal fully in embankment

• Canal partly in excavation and partly in embankment

Generally, the volume of earthwork for irrigational canals is calculated by the TRAPEZOIDAL formula which is also called End-area formula or the Mid-sectional formula. Generally, the side slope in CUTTING is kept as 1:1(H:V) and in BANKING 1.5:1(H:V) or 2:1(H:V) according to soil condition.
9.

Construction is the process of constructing a building or infrastructure.(a) True(b) FalseThe question was posed to me in semester exam.This is a very interesting question from Reports on Estimate for the Construction of Building and Culvert topic in portion Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Right choice is (a) True

The EXPLANATION is: Construction differs from manufacturing in that manufacturing typically involves mass production of SIMILAR items without a designated purchaser, while construction typically takes place on location for a known CLIENT. Construction as an industry comprises six to nine percent of the gross domestic PRODUCT of developed countries. Construction starts with planning, design, and financing; and continues until the project is built and ready for use.

10.

What is the capitalized value of a property fetching a net annual rent of Rs.1000 and the highest rate of interest prevalent being 5%, rate of interest is 8%?(a) Rs.16500.00(b) Rs.18500.00(c) Rs.12900.00(d) Rs.12500.00I had been asked this question in an online quiz.My question is taken from Values, Tax, Funds & Rents etc in division Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Correct answer is (d) Rs.12500.00

Explanation: For Rs.5.00 INTEREST, CAPITAL Rs.1000.00

To get Rs.1000.00 interest, capital = (100/5)*1000

= Rs.20000.00

In short capitalized value is – Net annual INCOME*Year’s purchase

For the same net income if the rate of interest is 8% the capitalized value = 1000*(100/8)= Rs.12500.00.

11.

What does CRF denote?(a) Central Research Fund(b) Central Road Fund(c) Capital Recovery Factor(d) Capital Recovery FundThis question was addressed to me in a job interview.I would like to ask this question from Design of Road Pavement topic in portion Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Right answer is (c) Capital Recovery Factor

Best EXPLANATION: The FIRST cost of a capital improvement is converted into equivalent annual cost which is called capital recovery factor. It is the ratio of a constant annuity to the present value of receiving that annuity for a given LENGTH of time.

 This is related to the annuity formula, which GIVES the present value in terms of the annuity, the interest rate, and the number of ANNUITIES.

12.

The average annual highway cost for a road system may be summed up by ________(a) Ca=H(b) Ca=H+T(c) Ca=H+T+M-Cr(d) Ca=H+T+M-CrI got this question in an interview for job.This interesting question is from Design of Road Pavement in chapter Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Correct CHOICE is (d) Ca=H+T+M-Cr

To ELABORATE: The average cost of the annual road system is the SUM of all costs LIKE average cost of highway administration, operation and MAINTENANCE and also the recovery fund.

13.

Quantity = Per capita sewage contributed per day x Population.(a) True(b) FalseThis question was addressed to me at a job interview.My question is from Principle for the Preparation of Water Supply in section Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

The correct answer is (a) True

To explain I WOULD say: Wastewater Quantity Estimation – The flow of sanitary sewage ALONE in the absence of storms in dry season is known as dry weather flow (DWF).

Sanitary sewage is mostly the spent WATER of the community draining into the sewer system. It has been observed that a small portion of spent water is lost in evaporation, seepage in GROUND, leakage, etc. Usually 80% of the water supply may be expected to REACH the sewers.

14.

The savings in annual road user costs, annual savings in accident costs and capital cost of Improvement are parameters used in ___________(a) annual cost method(b) rate of return method(c) benefit cost ratio(d) capital recovery fundThis question was posed to me by my school teacher while I was bunking the class.My enquiry is from Design of Road Pavement topic in chapter Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

The correct answer is (B) RATE of return method

To elaborate: The TRANSPORT laboratory of LONDON has DEVELOPED this method in which a rate of return is obtained by these parameters, the remaining methods don’t require these parameters.

15.

These are open drains provided for conveying water from kitchens, bathroom and rain water to main sewers.(a) Drains(b) Sewers(c) Soak pit(d) Surface drainsThe question was posed to me in an interview.Origin of the question is Principle for the Preparation of Water Supply topic in portion Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Right option is (d) Surface drains

The explanation is: These are usually provided at the side of the road and along the boundary line of the building. As far as possible drains should not be laid under the buildings. For EFFICIENT draining the surfacedrains should have certain qualities, such as should be laid in such a gradient to develop self -cleaning velocity, should have a reasonable FREE board at the top, joint should be SMOOTH finished, easy CURVES, INNER surface should be smooth, cheap in construction and maintenance.

16.

Design a low rate filter to treat 6.0 Mld of sewage of BOD of 210 mg/l. The final effluent should be 30 mg/l and organic loading rate is 320 g/m^3/d. Find Hydraulic loading rate?(a) 326.18 g/d/m^3(b) 926.18 g/d/m^3(c) 126.18 g/d/m^3(d) 526.18 g/d/m^3The question was asked during a job interview.This interesting question is from Principle for the Preparation of Water Supply in division Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Right answer is (a) 326.18 g/d/m^3

The explanation is: Assume 30% of BOD load removed in primary sedimentation i.e., = 210 X 0.30 = 63 mg/l. Remaining BOD = 210 – 63 = 147 mg/l.

Percent of BOD REMOVAL required = (147-30) x 100/147 = 80%

BOD load applied to the FILTER = flow x conc. of sewage (kg/d) = 6 x 106 x 147/106 = 882 kg/d

To find out filter volume, using NRC equation

Depth of filter = 1.5 m, Fiter area = 2704/1.5 = 1802.66 m^2, and Diameter = 48 m < 60 m

Hydraulic loading rate = 6 x 106/103 x 1/1802.66 = 3.33m3/d/m2 < 4 hence o.k.

Organic loading rate = 882 x 1000 / 2704 = 326.18 g/d/m^3 which is approx. equal to 320.

17.

Which is not a type of reservoir?(a) Small ground level reservoirs(b) Large ground level reservoirs(c) Underground reservoirs(d) Sub-surface reservoirI had been asked this question by my school teacher while I was bunking the class.My question is taken from Principle for the Preparation of Water Supply topic in division Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer» RIGHT OPTION is (d) Sub-surface reservoir

Best explanation: TYPES of Reservoirs-

i. Underground reservoirs.

ii. Small GROUND level reservoirs.

iii. LARGE ground level reservoirs.

iv. Overhead tanks.
18.

The number of treads in a flight is equal to _________(a) risers in the flight(b) risers plus one(c) risers minus one(d) risers plus threeI have been asked this question in a job interview.Question is from Structural Designing and Thumb Rules in division Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Correct answer is (c) risers MINUS one

Explanation: It is often not simply the sum of the individual tread lengths due to the nosing overlapping between TREADS. If there are N steps, the total RUN equals N-1 times the going: the tread of the last STEP is PART of a landing and is not counted.

19.

As the unevenness index increases there is no substantial increase in _____________(a) fuel consumption(b) wear and rear of tyres(c) vehicle maintenance cost(d) increase of speedThe question was posed to me in an interview for internship.My question is taken from Design of Road Pavement in section Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Correct choice is (d) increase of speed

For explanation I would say: As there is an increase in the UNEVENNESS index, there is no substantial increase in speed, instead it decreases.

Unevenness index is a measure of unevenness which is the cumulative measure of vertical undulations of the PAVEMENT surface recorded PER unit horizontal length of the road. An unevenness index value less than 1500 mm/km is considered as good, a value less than 2500 mm.km is satisfactory up to speed of 100 kmph and values greater than 3200 mm/km is considered as uncomfortable even for 55 kmph.

20.

High strength concrete is used in prestressed member?(a) To ovecome bursting stresses at the ends(b) To provide high bond stresses(c) To overcome cracks due to shrinkage(d) To overcome bursting stresses, provide high bond stresses and overcome cracksThis question was posed to me during an interview.This intriguing question originated from Structural Designing and Thumb Rules topic in portion Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer» CORRECT choice is (d) To overcome BURSTING stresses, PROVIDE high bond stresses and overcome cracks

Easy explanation: The PRIMARY DIFFERENCE between high-strength concrete and normal-strength concrete relates to the compressive strength that refers to the maximum resistance of a concrete sample to applied pressure. Although there is no precise point of separation between high-strength concrete and normal-strength concrete, the American Concrete Institute defines high-strength concrete as concrete with a compressive strength greater than 6,000 psi.
21.

Obsolescence is the annual periodic payments for repayments of the capital amount invested by a party.(a) True(b) FalseI have been asked this question in unit test.The question is from Values, Tax, Funds & Rents etc in portion Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Right option is (b) False

The best I can explain: An annuity is a series of payments made at equal intervals. Examples of ANNUITIES are regular deposits to a savings account, MONTHLY home mortgage payments, monthly insurance payments and PENSION payments. Annuities can be classified by the frequency of payment dates. The payments (deposits) may be made weekly, monthly, QUARTERLY, yearly, or at any other regular interval of time.

An annuity which provides for payments for the remainder of a person’s lifetime is a life annuity.

22.

Design a rectangular sedimentation tank to treat 2.4 million litres of raw water per day. The detention period may be assumed to be 3 hours. Find overflow rate?(a) 28,000 l/d/m^2(b) 12,000 l/d/m^2(c) 24,000 l/d/m^2(d) 4,670 l/d/m^2I had been asked this question during an interview for a job.Question is taken from Principle for the Preparation of Water Supply topic in section Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Correct answer is (C) 24,000 l/d/m^2

Easy explanation: Raw water flow per day is 2.4 x 106 l. Detention period is 3h.

Volume of TANK = Flow x Detention period = 2.4 x 103 x 3/24 = 300 m^3

Assume depth of tank = 3.0 m.

SURFACE area = 300/3 = 100 m^2

L/B = 3 (assumed). L = 3B.

3B2 = 100 m^2 i.e. B = 5.8 m

L = 3B = 5.8 X 3 = 17.4 m

Hence surface loading (Overflow rate) = 2.4 x 106 = 24,000 l/d/m^2 < 40,000 l/d/m^2.

23.

In water bound macadam roads, binding material is Brick dust.(a) True(b) FalseThe question was posed to me during an interview.The question is from Reports on Estimate for the Construction of Road and Irrigation Channel in chapter Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Right answer is (b) False

Easy explanation: Stone dust is like a DARKER, coarser version of sand. It is a byproduct of running stones through a crushing machine to make crushed stone. Its EXACT composition will obviously DEPEND on what kind of stone was run through the machine. For instance, sometimes granite is run through such a machine; in other cases, it could be limestone, for EXAMPLE. The machine has a screen that traps the larger material (that is, the crushed stone). The smaller material or “screenings” falls through the screen. Depending on the size of the holes in the screen USED, it can be so fine in texture that it is basically a powder.

24.

If the total quantity of earth obtained from digging in the bed is equal to the quantity of earth required for the formation of the banks then this is known as economic digging.(a) False(b) TrueThis question was addressed to me in semester exam.This question is from Reports on Estimate for the Construction of Road and Irrigation Channel in chapter Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Right choice is (a) False

For explanation I would SAY: Also this canal is said to be designed with the balancing depth. Quantity of DIGGING = Quantity in banking i.e. Sectional AREA of digging = Sectional area of two banks or, Bd+sd2 = (b1+b2)*h+2S1 h2. Although it is never possible to adjust the canal section to this requirement but it MAY be quite possible in certain portions.

If the quantity of earthwork in the excavation is more than the quantity of earthwork in banking then the surplus earth is thrown away to form spoil bank.

If the quantity of earthwork in the excavation is less than that of banking then the extra earth is taken from borrow pots in the temporary land WHOSE area is calculated for temporary land acquisition.

25.

In India the flexible pavement is designed as per _____________(a) CSA(b) FSA(c) KSA(d) MSAThis question was addressed to me in a job interview.The query is from Design of Road Pavement topic in chapter Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

The correct CHOICE is (d) MSA

To elaborate: The flexible pavements are designed as per IRC 37 which uses MSA to specify the unit of the vehicles.

MSA is defined as an experimental and MATHEMATICAL method of determining the amount of variation that exists within a measurement process. Variation in the measurement process can directly contribute to our overall process VARIABILITY. MSA is used to certify the measurement system for use by evaluating the system’s ACCURACY, precision and STABILITY.

26.

The design period of cement concrete road is taken as ____________(a) 30(b) 12(c) 5(d) 20This question was addressed to me in an internship interview.My enquiry is from Design of Road Pavement topic in section Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Correct answer is (a) 30

To explain: The design period of cement roads is usually taken as 30 years but they can even LAST longer if properly MAINTAINED and DESIGNED.

27.

The design life of flexible pavement is _________(a) 5(b) 8(c) 15(d) 30The question was asked during an interview.The question is from Design of Road Pavement topic in chapter Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Right option is (c) 15

To explain: The design life of flexible pavement is considered as 15 years, it may last even further if properly maintained.

The wheel load ACTING on the pavement will be distributed to a WIDER area, and the stress decreases with the depth. Taking advantage of this stress distribution characteristic, flexible pavements normally has many layers. Hence, the design of flexible pavement uses the concept of LAYERED system.

28.

The distribution pipes are generally laid below the road pavements, and as such their layouts generally follow the layouts of roads.(a) True(b) FalseThe question was asked during an online interview.The origin of the question is Principle for the Preparation of Water Supply topic in portion Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

The correct ANSWER is (a) True

The explanation: There are, in general, four different types of pipe networks; any one of which either singly or in combinations, can be used for a particular PLACE. They are: Dead END System, Grid IRON System, Ring System and RADIAL System.

29.

A ___________________ is a construction industry professional with expert knowledge on construction costs and contracts. They are not to be confused with Land Surveyors or Land Survey Engineers.(a) Project manager(b) Building services engineer(c) Quantity Surveyor(d) Civil estimatorsI have been asked this question in exam.I'd like to ask this question from Reports on Estimate for the Construction of Building and Culvert in section Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Right choice is (c) Quantity Surveyor

Easiest explanation: SERVICES provided by a quantity surveyor may include:

• Cost consulting, cost estimating

• Cost planning and commercial management throughout the entire life cycle of the project from inception to post-completion

• Value determination

• Risk management and calculation

• Procurement advice and assistance during the TENDERING procedures

• Tender analysis and agreement of the contract sum

• Commercial management and contract administration

• Assistance in dispute resolution

ASSET capitalisation

• Interim valuations and payment assessment

• Cost management process

• Assessing the additional COSTS of design variations.

30.

A ___________ can be used to span over a canyon, or depression, or even over a freeway or roadway.(a) culvert(b) tunnels(c) drainage(d) bridgesI had been asked this question in unit test.This intriguing question originated from Reports on Estimate for the Construction of Building and Culvert in portion Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Correct CHOICE is (B) tunnels

For explanation I WOULD SAY: A bridge doesn’t necessarily have to bridge over water. A bridge can be used to span over a canyon, or depression, or even over a freeway or roadway.

31.

The surface of the pavement should be _______(a) smooth(b) rough(c) sufficient enough to resist skid(d) very roughThe question was posed to me in an interview.The question is from Design of Road Pavement topic in portion Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

The CORRECT option is (c) sufficient ENOUGH to RESIST SKID

For explanation I would say: The surface of the pavement should be sufficient enough to resist the skid of vehicles by using FRICTION.

32.

A building costing Rs.700000.00 has been constructed on a freehold land measuring 100 sq m recently in a big city. Prevailing rate of land in the neighbourhood is Rs.150.00 per sq m. Determine the net rent of the property, if the expenditure on an outgoing including sinking fund is Rs.24000.00 per annum. Work out also the gross rent of the property per month.(a) 48000/-, 8000/-(b) 18000/-, 6000/-(c) 46700/-, 6000/-(d) 48000/-, 6000/-The question was posed to me in an international level competition.Question is taken from Values, Tax, Funds & Rents etc in portion Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Right answer is (d) 48000/-, 6000/-

To EXPLAIN: Cost of construction= Rs.700000.00

Cost of land @Rs.150.00 per sq m = 100*150 = Rs.150000.00

Net return:

On building @ 6% on the cost of construction = 700000.00 *6/100 = Rs.42000.00

On the land @ 4% on the cost of land = 700000.00 *6/100 =Rs.6000.00

Total net rent per YEAR =Rs.48000.00

Gross rent = Net rent + outgoings = 48000+24000.00 = 72000.00 per annum

Gross rent per month = 72000/12 = 6000.00.

33.

The advantage of reinforced concrete is due to ___________(a) monolithic character(b) moulding in any desired shape(c) fire-resisting and durability(d) monolithic character, moulding any shape and fire-resistingThe question was asked in semester exam.This intriguing question comes from Structural Designing and Thumb Rules topic in section Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Correct OPTION is (d) monolithic character, moulding any shape and fire-resisting

The best explanation: REINFORCED concrete (RC) is a composite material in which concrete’s relatively low tensile strength and DUCTILITY are counteracted by the inclusion of reinforcement having higher tensile strength or ductility. The reinforcement is usually, though not necessarily, steel reinforcing bars (rebar) and is usually embedded passively in the concrete before the concrete sets. Reinforcing schemes are generally designed to resist tensile stresses in particular regions of the concrete that might cause unacceptable cracking and/or structural FAILURE. Modern reinforced concrete can contain varied reinforcing materials made of steel, polymers or alternate composite material in conjunction with rebar or not. Reinforced concrete may also be permanently stressed (in TENSION), so as to improve the behaviour of the final structure under working loads.

34.

In this method, it is assumed that the property will lose its value by a constant percentage of its value at the beginning of every year. This method is called?(a) Sinking fund method(b) Constant percentage method(c) Straight line method(d) Quantity survey methodThe question was posed to me during an online exam.My doubt is from Values, Tax, Funds & Rents etc topic in portion Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

The correct choice is (c) Straight line method

The best I can EXPLAIN: In this method a FIXED AMOUNT of the original cost is deducted EVERY year so that at the end of the utility period only the scrap VALUE is left.

Annual depreciation D = Original cost-scrap value/life in year = C-S/n,

Where C- original cost, S- scrap value, n-life of the property in years and D- annual depreciation. The book value after the number of years, say N years = original cost – N*D.

35.

The architect is usually the lead designer on buildings, with a structural engineer employed as a sub-consultant.(a) False(b) TrueI had been asked this question during an internship interview.This intriguing question comes from Structural Designing and Thumb Rules in portion Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

The correct answer is (b) True

To explain: The degree to which each discipline ACTUALLY leads the design depends heavily on the type of STRUCTURE. MANY STRUCTURES are structurally simple and led by architecture, such as multi-storey office buildings and housing, while other structures, such as tensile structures, shells and gridshells are heavily dependent on their form for their strength, and the engineer may have a more SIGNIFICANT influence on the form, and hence much of the aesthetic, than the architect.

36.

Canals are natural-made channels for water conveyance, or to service water transport vehicles.(a) False(b) TrueThis question was addressed to me in examination.This question is from Reports on Estimate for the Construction of Road and Irrigation Channel in section Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Right option is (a) False

Explanation: Canals are human-made channels for water conveyance, or to service water transport vehicles. In most CASES, the ENGINEERED works will have a series of DAMS and locks that create areas of low speed current flow. These areas are referred to as slack water levels, often just CALLED levels.

An canal is also known as a navigation when it parallels a river and shares part of its waters and drainage basin, and leverages its resources by building dams and locks to INCREASE and lengthen its stretches of slack water levels while staying in its valley.

37.

The ICPB type of pavement uses _____________(a) concrete paver blocks(b) fly ash(c) rms(d) ggbsI got this question during an interview.The query is from Design of Road Pavement topic in chapter Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Correct answer is (a) concrete paver blocks

Explanation: The ICPB uses MOSTLY interlocking concrete paver blocks for the construction of pavements. Block paving also known as brick paving is a commonly used decorative method of creating a pavement or hardstanding. The main benefit of bricks over other materials is that individual bricks can later be lifted up and replaced. This allows for remedial work to be carried out under the surface of the paving without leaving a lasting mark once the paving bricks have been replaced. Typical areas of use would be for driveways, pavement, patios, town centres, precincts and more commonly in road SURFACING. Bricks are typically made of concrete or clay, though other composite materials are also used. Each has its own MEANS of construction. The biggest DIFFERENCE is the WAY they set hard ready for use. A clay brick has to be fired in a kiln to bake the brick hard.

38.

Find the plinth area required for the residential accommodation for an assistant engineer in the pay scale of Rs.400.00 to 1000.00 per month.(a) 293.33 sq m.(b) 93.33 sq m.(c) 983.33 sq m.(d) 23.33 sq m.I had been asked this question during an interview.This intriguing question comes from Values, Tax, Funds & Rents etc in portion Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

The correct choice is (b) 93.33 sq m.

The explanation is: AVERAGE pay = 400+1000/2 = Rs. 700.00 PER month.

Average monthly rent @ 10% of salary = 700.00/10 = Rs.70.00

Average annual rent 70.0*12 = Rs.840.00.

Capital cost of the building @ 6%interest = 840*100/6 = Rs.14000.00

PLINTH area required @Rs.150.00 per sq m of plinth area = 14000/150 = 93.33 sq m.

Normally the quarter for the assistant engineer should be constructed at the cost of Rs.14000.00 having plinth area of 93.33 sq m.

But due to the increase in the cost of construction, this may be increased by 100% and the capital cost of construction may be fixed as Rs.2800.00 and the APPROXIMATE plinth area of 93.33.

39.

A property fetches a net annual income of Rs.900 deducting all outgoings. Workout the capitalized value of the property if the rate of interest is 6% per annum.(a) Rs.67003.00(b) Rs.189003.00(c) Rs.45603.00(d) Rs.15003.00The question was posed to me in an interview for internship.This is a very interesting question from Values, Tax, Funds & Rents etc topic in division Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

The CORRECT CHOICE is (a) Rs.67003.00

The EXPLANATION: Year’s PURCHASE = 100/6 = 16.67

Capitalized value of the property = Net income * Y.P. = 900*16.67 = Rs.15003.00.

40.

Design of R.C.C. simply supported beams carrying U.D.L. is based on the resultant B.M. at ____________(a) mid span(b) supports(c) every section(d) quarter spanThis question was addressed to me by my college professor while I was bunking the class.Question is from Structural Designing and Thumb Rules in chapter Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer» RIGHT option is (a) mid SPAN

The explanation is: Since BM is maximum at midspan, design should be DONE for maximum bending moment so that it will take care for other SECTION. Moment formula we are USING is (wl2/8) which mid span moment.
41.

The maximum stress sustained by concrete pavements in kg/cm^2 is _________(a) 45(b) 30(c) 25(d) 15This question was addressed to me in an interview.The origin of the question is Design of Road Pavement topic in portion Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Right choice is (a) 45

For explanation: The CONCRETE pavements are designed to sustain a stress of 45Kg/cm^2 which is the maximum limit.

TEMPERATURE Stresses– DUE to the temperature differential between the top and bottom of the slab, curling stresses (SIMILAR to bending stresses) are induced at the bottom or top of the slab

 Frictional stresses– Due to the contraction of slab due to shrinkage or due to drop in temperature tensile stresses are induced at the middle portion of the slab. Wheel Load Stresses– CC slab is subjected to flexural stresses due to the wheel loads.

42.

The diameter of longitudinal bars of a column should never be less than?(a) 12 mm(b) 6 mm(c) 10 mm(d) 8 mmThe question was asked in an interview for internship.The query is from Structural Designing and Thumb Rules in division Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Correct answer is (a) 12 mm

Easiest explanation: Minimum diameter of LONGITUDINAL bar in RCC column shall not be less than 12mm (IS456:2000, cl 26.5.3.1 d). Indian standards SPECIFY 12mm as the least diameter of a vertical bar and 5mm as the least diameter of lateral bar or STIRRUP.

43.

As a modern technique use of plastics in canal lining is that plastic is covered at the top of the canal to prevent dust.(a) True(b) FalseThe question was asked by my school teacher while I was bunking the class.My query is from Reports on Estimate for the Construction of Road and Irrigation Channel in chapter Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Correct answer is (b) False

The best I can explain: The PLASTIC as a material for CANAL lining offers certain characteristic ADVANTAGES like negligible weight, easy for handling, spreading and transport, immune to chemical action and speedy construction. The plastic film is spread on the prepared subgrade of the canal. To anchor the membrane on the banks ‘V trenches are PROVIDED. The film is then COVERED with protective soil cover.

44.

The canal system does not consist ______________(a) main canal(b) branch canal(c) sub-main canal(d) major distributaryI got this question in my homework.This key question is from Reports on Estimate for the Construction of Road and Irrigation Channel topic in division Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Right choice is (c) sub-main canal

For explanation I would say: Main Canal-Main Canal takes off directly from the upstream side of WEIR head works or dam. Usually no DIRECT cultivation is proposed. Most of the main canals are aligned as contour canals to DERIVE benefit.

Branch Canal-All off takes from main canal with head DISCHARGE of 14-15 cumecs and above are termed as branch canals.

Major Distributary-All off takes from main canal or branch canal with head discharge from 0.028 to 15 cumecs are termed as major distributaries.

45.

An impermeable layer is provided at the bed and sides of canal to improve the life and discharge capacity of canal known as ______________(a) canal modification(b) canal concreting(c) canal lining(d) canal regulationI have been asked this question in exam.I'd like to ask this question from Reports on Estimate for the Construction of Road and Irrigation Channel topic in portion Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Correct option is (c) canal LINING

For explanation I would say: An important REASON for lining a canal can be the reduction in water losses, as water losses in unlined IRRIGATION canals can be high. Canals that carry from 30 to 150 liters/sec can lose 10 to 15% of this flow by seepage and water consumption by weeds. Lining a canal will not completely eliminate these losses, but roughly 60 to 80% of the water that is lost in unlined irrigation canals can be saved by a hard-surface lining. 42 Canal lining Minimizing water losses is very important, and especially so in schemes where irrigation water is pumped. Reduced water losses means LESS water to PUMP and thus a reduction in pumping costs.

46.

Which one is not a type of Equalization tanks?(a) Flow through type(b) Intermittent flow type(c) Variable inflow/constant discharge type(d) Intercept typeThe question was posed to me in unit test.The origin of the question is Principle for the Preparation of Water Supply in portion Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Right choice is (d) Intercept type

Best explanation: The simple flow through type equalization tank is mainly useful in assisting SELF neutralization or evening out of fluctuating concentrations, not for balancing of flows since a flow through type tank once filled, gives output equal to input.

Flow balancing and self-neutralization are both achieved by using two tanks, intermittently one after another. One tank is allowed to fill up after which it is checked for pH (or any other parameter) and then allowed to empty out. The second tank goes through a similar ROUTINE. INTERMITTENT flow type tanks are economic for small flows from industries.

When flows are large an equalization tank of such a SIZE may have to be provided that inflow can be variable while outflow is at a CONSTANT rate, generally by a pump.The capacity required is determined from a plot of the cumulative inflow and a plot of the constant rate outflow and measuring the gaps between the two plots. A factor of safety may be applied if desired.

47.

An old building has been purchased by a person at a cost of Rs.30000/- excluding the cost of the land. Calculate the amount of annual sinking fund at 4% interest assuming the future lie of the building as 20 years and the scrap value of the building as 10% of the cost of purchase.(a) Rs.979.7(b) Rs.4387.20(c) Rs.107.20(d) Rs.907.20I had been asked this question in an interview for internship.This key question is from Values, Tax, Funds & Rents etc in section Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Correct OPTION is (d) Rs.907.20

To elaborate: The total AMOUNT of sinking fund to be ACCUMULATED at the end of 20 years.

S = 30000 * 90/100 = Rs.27000.00

Annual instalment of sinking fund.

I = Si / [(1+i)n-1] = 27000*0.04/(1+0.04)20-1 = 27000*0.0336 = Rs.907.20

Annual Instalment for sinking fund REQUIRED for 20 years = Rs.907.20.

48.

If the span of crossing is greater than 12 feet (3.7 m), the structure is termed as bridge and otherwise is ______________(a) drainage(b) bridges(c) culvert(d) tunnelsThis question was addressed to me in an internship interview.Query is from Reports on Estimate for the Construction of Building and Culvert in portion Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Correct option is (c) culvert

To elaborate: A BRIDGE is a structure built to span physical obstacles without CLOSING the way underneath such as a body of water, valley, or road, for the PURPOSE of providing PASSAGE over the obstacle. There are many different DESIGNS that each serve a particular purpose and apply to different situations.

49.

A pumping set with a motor has been installed in a building at a cost of Rs.2500.00. Assuming the life of the pump as 15 years, work out the amount of annual instalment of sinking fund required to be deposited to accumulate the whole amount of 4% compound interest.(a) Rs.355(b) Rs.125(c) Rs.185(d) Rs.1950This question was posed to me during an internship interview.This question is from Values, Tax, Funds & Rents etc topic in section Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Correct choice is (b) Rs.125

The explanation is: The annual sinking FUND, I = Si / [(1+i)n-1] = 2500*0.04/(1+0.04)15-1 = 2500*0.05 = Rs.125

The OWNER is to deposit Rs.125/- annually in 4% compound interest carrying investment for 15 YEARS to accumulate Rs.2500/-.

50.

Skilled occupations include carpenters, electricians, plumbers, ironworkers, masons, and many other manual crafts, as well as those involved in project management.(a) True(b) FalseThe question was posed to me in an interview for job.My question comes from Reports on Estimate for the Construction of Building and Culvert in division Valuation, Reports Technical and Design Data of Civil Engineering Drawing

Answer»

Correct answer is (a) True

Best explanation: There are many routes to the different careers WITHIN the construction industry. These three main tiers are based on EDUCATIONAL background and training, which vary by country:

• Unskilled and semi-skilled – General site LABOR with little or no construction qualifications.

• Skilled – Tradesmen who’ve served apprenticeships, TYPICALLY in labor unions, and on-site managers who possess extensive knowledge and experience in their craft or profession.

• Technical and management – Personnel with the greatest educational qualifications, usually graduate degrees, trained to design, manage and instruct the construction process.