1.

1). 102). 123). 154). 8

Answer»

Let, No. of men initially = x

x men can COMPLETE the work in 10 days.

∴ Total work = 10x

Work done in 4 days = 4X

∴ Remaining work = 10x – 4x = 6x

According to problem, (x – 6) COMPLETED the remaining work in = 12 days

∴ 12(x – 6) = 6x

⇒ 6x = 72

⇒ x = 12

∴ Initially there were 12 men.