InterviewSolution
This section includes InterviewSolutions, each offering curated multiple-choice questions to sharpen your knowledge and support exam preparation. Choose a topic below to get started.
| 1. |
Pipe A can fill the tank in 45 min and pipe B can empty the tank in 1 hour 30 min. If pipe B is opened after 30 min of start of pipe A, what is the total time required to fill the tank?1). 1 hour2). 1 hour 10 min3). 1 hour 20 min4). 1 hour 30 min |
|
Answer» Time require to fill the tank by pipe A = 45 MIN Time require to empty the tank by pipe B = 1 hour 30 min = 60 + 30 = 90 min Amount of tank FILLED in 30 min by pipe A, ⇒ Amount of tank filled = (1/45) × 30 = 2/3 ⇒ Remaining part of tank = 1 - 2/3 = 1/3 For time require to fill the tank, ⇒ (1/45 - 1/90) × t = 1/3 ⇒ [(2 - 1)/90] × t = 1/3 ⇒ (1/90) × t = 1/3 ⇒ t = (1/3) × (90) ⇒ t = 30 min ∴ Total time taken = 30 min + 30 min = 1 hour |
|
| 2. |
1). 502). 443). 564). 54 |
|
Answer» The ratio of EFFICIENCIES of P, Q and R is 4 : 3 : 8. Let their efficiencies be 4T, 3T and 8T, respectively. Their total efficiency will be 15T. We know, TIME to finish work is INVERSELY proportional to efficiency. ⇒ 4.5 × 3T = Time REQUIRED × 15T ⇒ Time required = 4.5/5 = 0.9 hours = 54 minutes |
|
| 3. |
A man is twice as fast as a woman and a woman is twice as fast as a boy. If all of them i.e. a man, a woman and a boy can finish a work together in 4 days, in how many days a boy shall do it alone?1). 28 days2). 21 days3). 14 days4). 7 days |
|
Answer» ASSUME the efficiency of a boy = B units/day As a woman is TWICE as fast as a boy so the efficiency of a woman = 2B units/day As a man is twice as fast as a woman so the efficiency of a man = 4B units/day According to the question, all of them i.e. a man, a woman and a boy can finish a work together in 4 days. In 4 days total work done by a man, a woman and a boy = 4 × (B + 2B + 4B) = 28B units. ∴ Total work = 28B units. Time required for a boy to do the whole work alone = $(\FRAC{{Total\;work\;}}{{efficiency\;of\;a\;boy}}\; = \frac{{28B}}{B} = 28\;days)$ Time required for a boy to do the whole work alone = 28 days. |
|
| 4. |
Quantity B: B can complete the work in 20 days. C is twice as efficient as B and A takes 2 days more than C to complete the work. Working together, in how much time would they be able to complete the work?1). Quantity A > Quantity B2). Quantity A < Quantity B3). Quantity A ≥ Quantity B4). Quantity A ≤ Quantity B |
|
Answer» Quantity A: Let total work be 120 units (LCM of 24, 30 & 40) ⇒ Work done by A in one day = 120/24 = 5 units ⇒ Work done by B in one day = 120/30 = 4 units ⇒ Work done by C in one day = 120/40 = 3 units ⇒ Work done by A and B in 1 day = (5 + 4) = 9 units ⇒ Work done by A and B in 6 days = 9 × 6 = 54 units ⇒ Remaining work = 120 – 54 = 66 units ⇒ Work done by A, B and C together in 1 day = 5 + 4 + 3 = 12 units ⇒ Time taken by A, B & C together to complete the remaining 66 units of work = 66/12 = 5.5 days ⇒ Total time taken = 6 + 5.5 = 11.5 days Quantity B: ⇒ Time taken by B to complete the work = 20 days ⇒ Time taken by C to complete the work = 20/2 = 10 days ⇒ Time taken by A to complete the work alone = 10 + 2 = 12 days Let total work be 60 units (LCM of 12, 20 & 10) ⇒ Work done by A in one day = 60/12 = 5 ⇒ Work done by B in one day = 60/20 = 3 ⇒ Work done by C in one day = 60/10 = 6 ⇒ Work done by A, B and C together in 1 day = 5 + 3 + 6 = 14 units ⇒ Time taken by A, B and C together to complete the work = 60/14 = 30/7 days ∴ Quantity A > Quantity B |
|
| 5. |
96 men can complete a work in 40 days. They all worked for 10 days. But to finish the work before time, contractor brought N more men to work. Because of this, the work got finished in a total of 34 days. What is the value of N?1). 162). 203). 244). 27 |
|
Answer» The total number of man-days will be same in both the cases. ⇒ 96 × 40 = 96 × 10 + (96 + N) × (34 – 10) ⇒ 3840 = 960 + 2304 + 24N ⇒ N = 576/24 = 24 |
|
| 6. |
Kamal can do a work in 20 days. Bimal is 20% more efficient than Kamal. Suresh is 25% more efficient than Bimal. The number of days, Suresh will take to do the same piece of work, is1). 16 days2). 12 days3). \(15\frac{2}{3}\) days4). \(13\frac{1}{3}\) days |
|
Answer» Number of days Kamal TAKES to complete a WORK = 20 days ∴ In 1 day Kamal can do = 1/20 part of work Given: Bimal is 20% more EFFICIENT than Kamal ∴ In 1 day Bimal can do = 1.2/20 part of work Given: SURESH is 25% more efficient than Bimal ∴ In 1 day Suresh can do = $(\frac{{1.2\; \times \;1.25}}{{20}})$ part of work ∴ Suresh can do the complete work in $(\frac{{20}}{{1.2 \times 1.25}} = 13\frac{1}{3})$ days |
|
| 7. |
A is 25% more efficient then B. A works for ‘D’ days and completed 1/3 of work and left the work and remaining work is completed by B in ‘D + 12’ day. In how many days A and B together can complete the work.1). 15 days2). \(13\frac{1}{3}days\)3). 12 days4). \(12\frac{1}{3}days\) |
|
Answer» A works for D days and completed 1/3rd of WORK Work done by A in D days = 1/3 A alone can complete the work = 3D days Work done by A in 1 day = (1/3) × (1/D) = 1/3D Ratio of time taken by A and B = 100 : 125 Let’s assume B alone can complete the work in in x days. ⇒ 100 / 125 = 3D/x ⇒ x = 15D/4 Remaining work = 1 - 1/3 = 2/3 2/3rd of work completed by B in (D + 12) days. ⇒ 2/3 = (4/15D) × (D + 12) ⇒ 30D = 12D + 144 ⇒ 18D = 144 ⇒ D = 8 A can alone complete the work in 8 × 3 = 24 days B alone can complete the work in = 15/4 × 8 = 30 If A and B work TOGETHER, work will be completed in = 1/[(1/24) + (1/30)] = 1/(9/120) = 120/9 ∴ A and B together complete the work in 120/9 = $(13\frac{1}{3})$ Days |
|
| 8. |
1). 60/11 hours2). 60/17 hours3). 30/23 hours4). 24 hours |
| Answer» | |
| 9. |
Nikhil is thrice as efficient as Kanak and can finish an assignment in 6 days less than Kanak. How many days Kanak will take to finish the same assignment?1). 4 days2). 7 days3). 9 days4). 11 days |
|
Answer» Efficiency of Nikhil : Efficiency of Kanak = 3 : 1 Nikhil will TAKE 1/3 time as compared to Sunita Let us ASSUME Kanak will take 3x DAYS to COMPLETE an assignment and Nikhil will take x days. ⇒ 3x - x = 6 ⇒ x = 3 ∴ Kanak will take 3 × 3 = 9 days |
|
| 10. |
1). 14 hours2). 42 hours3). 35 hours4). 70 hours |
|
Answer» Let PIPES P and Q take p and q HOURS respectively to fill the cistern. From the question, p = 2Q----(1) They fill TOGETHER the tank in 28 hours. $(\begin{ARRAY}{l} \therefore \frac{1}{p} + \frac{1}{q} = \frac{1}{{28}}\\ \Rightarrow \frac{1}{{2q}} + \frac{1}{q} = \frac{1}{{28}}\\ \Rightarrow \frac{{3}}{{2{q}}} = \frac{1}{{28}} \end{array})$ ⇒ 2q = 84 ∴ q = 42 hours |
|
| 11. |
Resting 8 hours per day, Anuj can walk a certain distance in 15 days. How long will he take to walk twice the distance, twice as fast where he rests twice as long each day?1). 30 days2). 40 days3). 50 days4). 120 days |
|
Answer» Let the distance to be travelled be ‘d’. ⇒ Anuj walks d distance in 15 days while resting 8 hours a DAY 1 day = 24 hours Number of hours Anuj walks in a day = 24 – 8 = 16 hours ∴ Time TAKEN to walk d distance = 16 × 15 = 240 hours ∴ SPEED = d/240----(1) New distance, d’ = 2D New speed = 2 × speed = 2d/240 = d/120 Resting hours = 2 × 8 = 16 hours ⇒ Number of working hours in a day = 24 – 16 = 8 hours Time taken to walk 2d distance = 2d/(d/120) = 240 hours ∴ Number of days to walk distance 2d = 240/8 = 30 days |
|
| 12. |
1). 582). 603). 554). 66 |
|
Answer» Rahi is 30% less EFFICIENT than Tanu. Tanu TAKES 99 days to COMPLETE a work. ∴ NUMBER of days TAKEN by Rahi to finish a work = $(\frac{{99}}{{100 - 30}} \times 100 = \frac{{990}}{7}\;days)$ In one day, together they do = $(\frac{1}{{99}} + \frac{7}{{990}} = \frac{{17}}{{990}})$ ∴ Time taken to do complete work = 990/17 ≈ 58 days |
|
| 13. |
Time taken by A and B to complete a work is in the ratio 2 : 3. A alone worked for 5 days and left the work then B alone worked for 10 days on the same work, It is found than 70% of the work is completed. Find the time in which they together can complete the work.1). 10 days2). 15 days3). 8 days4). 200/13 days |
|
Answer» Ratio of time taken by A and B to complete a work = 2 ? 3 ∴ Ratio of EFFICIENCY of A and B = 3 ? 2 Let, efficiency of A = 3X/day and efficiency of B = 2x/day Let, quantity of total work = a According to problem, ⇒ 5 × 3x + 10 × 2x = 0.7a ⇒ 0.7a = 35x ⇒ a = 50x Let, they together do the work in = y days ⇒ y × (3x + 2x) = 50x ⇒ y = 50x/5x ⇒ y = 10 ∴ They together will complete the work in = 10 days |
|
| 14. |
1). 10 days2). 13 days3). 17 days4). 30 days |
|
Answer» Let Jake can FINISH the piece of WORK alone in x days. ∴ ASHLEY can alone finish the work in x/2 days. In 1 DAY Jake can do work = 1/x In 1 day Ashley can do work = 1/(x/2) = 2/x 1/x + 2/x = 1/20 ⇒ 3/x = 1/20 ⇒ x = 60 ∴ Ashley alone can finish the work in 60/2 i.e. 30 days |
|
| 15. |
1). 65 days2). 70 days3). 56 days4). 55 days |
|
Answer» Shivi is 20% less efficient than Manik. Manik takes 60 DAYS to complete a work. ∴ Number of days taken by Shivi to finish a work = $(\FRAC{{60}}{{100 - 20}} \times 100 = 75\;days)$ By Unitary method, Work done by Shivi in ONE day = 1/75 Similarly, work done by Manik in one day = 1/60 Work done by Shivi on first two days = 2/75 = 2/75 Work done by Manik on third day =$(\;\frac{1}{{60}})$ ∴ TOTAL work done in a span of three days = $(\frac{2}{{75}} + \frac{1}{{60}} = \frac{{8 + 5}}{{300}} = \frac{13}{{300}})$ ∴ Total number of complete spans = Integer part of $(\frac{{300}}{13} = 23)$ Remaining work = $(1 - \left( {23 \times \frac{13}{{300}}} \right) = \frac{1}{{300}})$ After completion of three day cycle, once again Shivi will work on first two days. ∴ Time taken by Shivi to complete $(\frac{1}{300})$work = $(\frac{1}{{300}} \times 75 = 1/4\;days)$ which is less than 2 days. ∴ Approximate total number of days taken to complete the work = (23 × 3 + (1/4)) = 69.25 days ≈ 70 days |
|
| 16. |
If 12 furnaces consume 13 tonnes of coal in \(6\frac{1}{2}\) hours, how long will 7 furnaces be consuming 14 tonnes?1). 11 hrs2). 10 hrs3). 12 hrs4). 15 hrs |
|
Answer» Concept: If M1 Persons can do a work W1 in H1 hours and M2 persons can do a work W2 in H2 hours then we have a general formula in this case. $(\frac{{{M_1}{H_1}}}{{{W_1}}} = \frac{{{M_2}{H_2}}}{{{W_2}}})$ If 12 furnaces consume 13 tonnes of coal in $(6\frac{1}{2})$ hours, then for 7 furnaces for consuming 14 tonnes We have, M1 = 12 furnaces W1= 13 tones H1 = $(6\frac{1}{2} = \frac{{13}}{2}\;hours)$ M2 = 7 furnaces W2 = 14 tones Let H2 = H hours By putting all these values in the above general formula $(\begin{array}{l} \frac{{12 \times \frac{{13}}{2}}}{{13}} = \frac{{7 \times H}}{{14}}\\ \RIGHTARROW \;H\; = \frac{{12 \times 13 \times 14}}{{2 \times 7 \times 13}} = 12hours\; \end{array})$ |
|
| 17. |
1). 2 days2). 4 days3). 6 days4). 8 days |
|
Answer» Work done by Imran in ONE day = 1/12 Work done by Hashim in one day = 1/36 Work done by Rajat in one day = 1/18 Work done by Imran and Hashim TOGETHER in one day = (1/12) + (1/36) = 1/9 Work done by Imran and Rajat together in one day = (1/12) + (1/18) = 5/36 Work done in 2 DAYS = (1/9) + (5/36) = 1/4 Time taken to COMPLETE the work = 2/(1/4) = 2×4 = 8 days |
|
| 18. |
A can do a piece of work in 80 days. He works at it for 10 days and then B alone finishes the remaining work in 42 days. In how much time will A and B, working together, finish the work?1). 30 days2). 32 days3). 26 days4). 27 days |
|
Answer» A can do a PIECE of WORK in 80 days. $(\begin{array}{l} {\rm{Work\;done\;by\;A\;in\;}}1{\rm{\;days}} = \frac{1}{{80}}\\ {\rm{Work\;done\;by\;A\;in\;}}10{\rm{\;days}} = \frac{1}{{80}}{\rm{\;}} \times 10 = \frac{1}{8}\\ \THEREFORE {\rm{Remaining\;work\;to\;be\;done\;by\;B}} = 1 - \frac{1}{8} = \frac{7}{8}\\ \frac{7}{8}{\rm{\;of\;the\;work\;is\;done\;by\;B\;in\;}}42{\rm{\;days\;}}\\ \therefore {\rm{Complete\;work\;is\;done\;by\;B\;in}} = 42{\rm{\;}} \times \frac{8}{7} = 6 \times 8 = 48{\rm{\;days\;}}\\ {\rm{Work\;done\;by\;A\;in\;}}1{\rm{\;day}} = \frac{1}{{80}}{\rm{\;and\;work\;done\;by\;B\;in\;}}1{\rm{\;day}} = \frac{1}{{48}}\\ \therefore {\rm{A\;and\;B's\;}}1{\rm{\;day's\;work}} = \frac{1}{{80}} + \frac{1}{{48}} = \frac{8}{{240}} = \frac{1}{{30}} \end{array})$ ∴ Both will finish the work in 30 days. |
|
| 19. |
If two pipes P and Q are such that, they can fill a large tub in 6 and 18 minutes respectively. They are opened on alternate minutes. Find in how many minutes, the tub shall be full?1). 6 min.2). 10 min.3). 18 min.4). 24 min. |
|
Answer» TIME-taken by PIPE P to fill the tub = 6 mins ∴ Part of tub filled by Pipe P in one minute = 1/6 Time-taken by pipe Q to fill the tub = 18 min. ∴ Part filled by Pipe Q in one minute = 1/18 The part of tank filled in a span of 2 minutes $(= \;\frac{1}{6} + \frac{1}{{18}} = \frac{4}{{18}} = \frac{2}{9})$ ∴ part of tub filled in 8 minutes $(= \;4\; \times \frac{2}{9}\; = \frac{8}{9})$ ⇒ Part of tub left to be filled = 1 – (8/9) = 1/9 After 8 minutes, it’s pipe A’s turn to fill the tub and 1/9th part of the tub is empty. Pipe A fills the entire tub in 6 minutes, so the time taken by pipe A to fill 1/9th of tub = 6/9 min. ⇒ Total time taken $(= 8 + \frac{6}{9} = 8\frac{2}{3}minutes)$ |
|
| 20. |
Consider three pipes P, Q and R. The pipes P and Q can fill the cistern in 2 and 2.5 hours respectively. The pipe R can empty the cistern in 1 hour. If these pipes were opened at an interval of half an hour at 6:00am, 6:30am and 7:00am respectively. When the cistern will get empty?1). 7:00 am2). 10:00 am3). 12:00 pm4). 2:00 pm |
|
Answer» Amount EMPTIED by pipe R in one hour = 1 As pipe P fills the entire cistern in 2 hours, PART of cistern FILLED by pipe P in one hour = ½ As pipe Q fills the entire cistern in 2.5 hours, Amount filled by pipe Q in one hour = 1/2.5 For the first half an hour only pipe P is open. ∴ Part of cistern filled by pipe P in starting ½ hour = ½ × ½ = ¼ For the next half an hour, pipe P and pipe Q both are open. ∴ Part of cistern filled by pipe P and pipe Q in next half an hour $(= \frac{1}{2}\left( {\frac{1}{2} + \frac{2}{5}} \right) = \frac{1}{4} + \frac{1}{5} = \frac{9}{{20}})$ ∴ Total pat of cistern filled after one hour $(= \frac{1}{4} + \frac{9}{{20}} = \frac{7}{{10}})$ After 1 hour all three PIPES are open. Let x be the number of hours for which all 3 pipes are open ∴ At the end of x hours, the cistern will be completely empty ∴ $(\frac{7}{{10}} + x\left( {\frac{1}{2} + \frac{1}{{2.5}} - \frac{1}{1}} \right) = 0)$ $(\Rightarrow \frac{7}{{10}} - \frac{x}{{10}} = 0)$ ⇒ x = 7 ∴ All three tanks are open for 7 hours. ⇒ Tank will get empty 7 hours after 7:00 am. ⇒ Tank will get empty at 2:00 pm. |
|
| 21. |
1). 80 min2). 75 min3). 50 min4). 100 min |
|
Answer» Total capacity of Cistern = LCM of 25, 20 and 10 = 100 units Efficiency of pipe 1 = 100/25 = 4 units/min Efficiency of pipe 2 = 100/20 = 5 units/min Efficiency of pipe 3 = - 100/10 = -10 units/min Efficiency of pipe 1, pipe 2 and pipe 3 together = 4 + 5 - 10 = -1 units/min ∴ TIME taken to empty the cistern = 100/1 = 100 min |
|
| 22. |
A cistern is filled in 4 hours and it takes 6 hours when there is a leak in its bottom. How long will the leak take to empty the full cistern?1). 6 hrs2). 5 hrs3). 12 hrs4). 10 hrs |
|
Answer» Given, Time to FILL the CISTERN without leak = 4 hrs ∴ Part FILLED without leak in 1 hour = 1/4 Time TAKEN to fill the cistern with leak = 6 hrs ∴ Part filled with leak in 1 hour = 1/6 ∴ Part emptied by leak in 1 hour = 1/4 - 1/6 = 1/12 ∴ Total time to taken to empty the cistern by the leak = 12 hrs |
|
| 23. |
1). 172). 163). 144). 13 |
|
Answer» (A + B)’s 2 day’s work $( = \FRAC{1}{{15}} + \frac{1}{{20}} = \frac{7}{{60}})$ Work done in 8 pairs of DAYS $( = \left\{ {\frac{7}{{60}} \times 8} \RIGHT\} = \frac{{14}}{{15}})$ REMAINING work $( = \left\{ {1 - \frac{{14}}{{15}}} \right\} = \frac{1}{{15}})$ Work done by A on 17th day $( = \frac{1}{{15}})$ Total time taken = 17 days. |
|
| 24. |
Aman takes thrice as much time as Baman to do a piece work. If they working together the work will be completed in 12 days. Then Baman can do the work alone in1). 24 days2). 48 days3). 16 days4). 28 days |
|
Answer» LET Baman takes X DAYS to complete the work then AMAN will TAKE 3X days to complete it. ∴ 1/X + 1/3X = 1/12 X = 16 days |
|
| 25. |
The ratio of efficiencies of Gary, Sunny and Allan is 3 : 2 : 7. Gary and Sunny work for a week. After that, Sunny leaves and Allan joins Gary. After one more week, the work gets finished. In how many days can Sunny finish the work if he works alone?1). 152). 353). 52.54). 75 |
|
Answer» The ratio of efficiencies of Gary, Sunny and Allan is 3 : 2 : 7. Suppose Gary, Sunny and Allan finish WORK alone in T/3, T/2 and T/7 DAYS, respectively. Work done in one day by Gary, Sunny and Allan will be 3/T, 2/T and 7/T, respectively. Gary and Sunny work for a week. After that, Gary leaves and Allan JOINS Sunny. After one more week, the work GETS finished ⇒ Work done in FIRST week = 7 × (3/T + 2/T) = 35/T ⇒ Work done in second week = 7 × (3/T + 7/T) = 70/T ⇒ 35/T + 70/T = 1 ⇒ T = 105 ∴ Number of days in which Sunny finish works alone = T/2 = 105/2 = 52.5 days |
|
| 26. |
Five men A, B, C, D and E can do a piece of work in 20, 10, 30, 40 and 50 days respectively. A, B, and C started the work and they work for 2 days after which A and B left the work and D joins the work. D and C work another 3 days together after which C leaves and E joins the work. Find in how many days E and D completed the rest of the work.1). 10.2 days2). 12.64 days3). 20.5 days4). 11.48 days |
||||||||||||||||||
|
Answer» Let the total units of WORK be 600
A, B, and C started the work and they work for 2 days ⇒ Number of units PRODUCED in TWO days by A, B and C = (30 + 60 + 20) × 2 = 220 units Then A and B left the work and D and C work another 3 days together ⇒ Number of units produced in 3 days by D and C = (15 + 20) × 3 = 35 × 3 = 105 units ⇒ Work left for D and E = 600 – 220 – 105 = 275 units ∴ D and E will complete REST of the task in 275/(15 + 12) days = 10.2 days |
|||||||||||||||||||
| 27. |
1). 122). 163). 184). 20 |
|
Answer» B’s 1 day work = 1/15 Hence, B’s 5 DAYS work $( = \frac{5}{{15}} = \frac{1}{3})$ Work remaining $(= \left\{ {1 - \frac{1}{3}} \right\} = \frac{2}{3})$ 2/3 of the work can be DONE by A in $(\left\{ {\frac{2}{3} \times 24} \right\} = 16)$ |
|
| 28. |
The capacity of a cuboidal container is 3000m3. A pump can be used to fill as well as to empty the container. The emptying capacity of the container is ___ and emptying capacity of the container is 15m3 per minute higher than its filling capacity and the pump needs 10 minutes lesser to empty the container than it need to fill it.1). 602). 803). 504). 45 |
|
Answer» Let the filling capacity of the CONTAINER = x m3 Emptying capacity = (x + 15) m3 ⇒ 3000/x – 3000/(x + 15) = 10 ⇒ 3000x + 45000 – 3000x = 10x(x + 15) ⇒ 45000 = 10x2 + 150X ⇒ x2 + 15x – 4500 = 0 ⇒ x = 60 , -75 (It can be neglected) ∴ Emptying capacity = x + 15 = 75 |
|
| 29. |
1). Rs. 1502). Rs. 2253). Rs. 2604). Rs. 300 |
|
Answer» PART of the work done by KHALEESI = (1/15 × 6) = 2/5 Part of the work done by John Snow = (1/12 × 6) = 1/2 Part of the work done by Cersi = 1 – (1/2 + 2/5) = 1/10 ∴, (Khaleesi’s share) : ( John’s share) : (Cersi’s share) = 2/5 : ½ : 1/10 = 4 : 5 : 1 ∴ Khaleesi’s share = (4/10 × 2400) = Rs.960 John’s share = (5/10 × 2400) = Rs.1200 Cersi’s share = (1/10 × 2400) = Rs.240 Now, Khaleesi’s daily WAGES = Rs. (960/6) = Rs.160 John’s daily wages = Rs. (1200/6) = Rs.200 Cersi’s daily wages = Rs. (240/4) = Rs.60 ∴ Daily wages of john and cersi are (60 + 200) Rs.260. |
|
| 30. |
Quantity B: 51). Quantity A > Quantity B2). Quantity A ≥ Quantity B3). Quantity B > Quantity A4). Quantity B ≥ Quantity A |
|
Answer» Quantity A:$ Let Sammy can complete a piece of work in ‘x’ hours TIME TAKEN by Billy to complete the work = (2x) hours ⇒ (x + 6) = 2x ⇒ x = 6 hours Work done by Sammy in ONE hour = 1/x = 1/6 Work done by Billy in one hour = 1/2x = 1/12 Work done by Sammy and Billy together in one hour = (1/6) + (1/12) = 1/4 Time taken by both Sammy and Billy to complete the work together = 1/(1/4) = 4 hours ∴ Time taken by both Sammy and Billy to complete the work together = 4 hours Quantity B: 5 Quantity B > Quantity A |
|
| 31. |
Ojha and Bali together can complete a work in 10 days. Ojha alone can complete it in 18 days. If Bali now does the work only for half a day daily, then in how many days Ojha and Bali together will complete the work?1). 13 days2). 11 days3). 12 days4). 10 days |
|
Answer» Work DONE by Ojha in ONE day = 1/18 Work done by Ojha and BALI together in one day = 1/10 Work done by Bali in one day = (1/10) – (1/18) = 2/45 Work done by Bali in one day if he works for only half day = 2/(2×45) = 1/45 Work done by Ojha and Bali together if Bali works only for half a day daily in one day = (1/18) + (1/45) = 7/90 Time taken by Ojha and Bali to complete the work together when Bali works only for half a day = 1/(7/90) = 90/7 ≈ 13 days |
|
| 32. |
Aman and Barkha together work for 6 days and leave the job. Chandan can do the whole work in 30 days. If the ratio of their efficiency is 3 : 6 : 2, then in how many days can Chandan alone finish the remaining work?1). 16 days2). 18 days3). 12 days4). 14 days |
|
Answer» Ratio of their efficiency = 3 : 6 : 2 Days of completion ratio = 1/3 : 1/6 : 1/2 = 2 : 1 : 3 3 ⇒ 30 1 ⇒ 10 2 ⇒ 20 Part of work done by A and B in 6 days = (6/10 + 6/20) = 18/20 = 9/10 Remaining work = (1 – 9/10) = 1/10 ∴ 1/10 of work will be completed by C in 3 days. |
|
| 33. |
A bucket can be filled by a pipe in 10 minutes and by another pipe in 40 minutes. Both the pipes are kept open for 5 minutes and then first pipe is closed. After this, how much time will be required to fill the complete bucket?1). 30 minutes2). 10 minutes3). 15 minutes4). 25 minutes |
|
Answer» PART filled by PIPE A in 1 minute = 1/10 Part filled by pipe B in 1 minute = 1/40 (A + B)’s 10 minute work = 5 × (1/10 + 1/40) = 5/8 REMAINING work = 1 – 5/8 = 3/8 ⇒ 1/40 : 3/8 = 1 : x ⇒ 1/15 = 1/x ⇒ x = 15 ∴ remaining time is 15 MINUTES |
|
| 34. |
1). Rs. 2002). Rs. 3003). Rs. 4004). Rs. 250 |
|
Answer» Suppose TOTAL work = 72 UNITS (LCM of 24, 36 and 3) ⇒ Efficiency of Sumit = 72/3 = 24 ⇒ Efficiency of the 1st SON = 72/24 = 3 ⇒ Efficiency of the 2nd son = 72/36 = 2 Suppose the efficiency of the 3rd son = x Since Sumit can do TWICE the work as much as done by all the 3 sons together ⇒ 24 = 2 × (3 + 2 + x) ⇒ x = 7 ⇒ Ratio in which the amount will be distributed among the 3 sons = 3 ? 2 ? 7 ∴ Share of the 3rd son = 600 × 7/12 = RS. 350 |
|
| 35. |
If 8 men and 9 women can do a piece of work in 8 days while 26 men and 48 women can do the same in 2 days, the time taken by 15 men and 10 women in doing the same type of work will be:1). 3 days2). 4 days3). 5 days4). 6 days |
|
Answer» If m1MEN and w1woman working together can do a piece of work in d1 days, and m2men and w2 women working together can do it in d2 days men are p times efficient than women then ⇒ d1/d2 = (pm2 + w2)/(pm1 + w1) ⇒ 8/2 = (26P + 48)/(8p + 9) ⇒ 32p + 36 = 26p + 48 ⇒ 6p = 12 ⇒ P = 2 ∴ Time taken by 15 men and 10 women in doing it will be = 8 × {[(2 × 8) + 9]/[(2 × 15) + 10)]} = 5 days |
|
| 36. |
A cistern is normally filled by a tap in 5 hours, but suddenly a leak develops and it empties the full cistern in 30 hours with the leak, the cistern is filled in1). 8 hours2). 6 hours3). 10 hours4). 7.5 hours |
|
Answer» WORK DONE by a tap in one HOUR = 1/5 Work done by leak in one hour = 1/30 Total work done in 1 hour = {(1/5) – (1/30)} = 1/6 ∴ Required time = 6 HOURS |
|
| 37. |
1). Rs. 30002). Rs. 45003). Rs. 60004). Rs. 7200 |
|
Answer» Let the efficiency Q be T. P works twice as FAST as Q. ⇒ Efficiency of P = 2T Also, Q and R together can finish a work together in one third of the time in which Q finishes the work alone. ⇒ Efficiency of Q + Efficiency of R = 3 × Efficiency of Q ⇒ Efficiency of R = 2 × Efficiency of Q = 2T We know, share of a person is PROPORTIONAL to his efficiency. ⇒ Share of Q = (Efficiency of Q/Sum of efficiencies of P, Q and R) × Rs. 30000 ⇒ Share of Q = T/(2T + T + 2T) × Rs. 30000 = Rs. 6000 |
|
| 38. |
9 men working for 7 hours a day can complete a piece of work in 20 days, in how many days can 7 men working for 10 hours a day complete the same piece of work?1). 21 days2). 22 days3). 20 day4). 18 days |
|
Answer» We know that WORK = M × D × H Here, M = no. of men D = no of DAYS H = hours So, M1 × D1 × H1 = M2 × D2 × H2 9 × 20 × 7 = 7 × D2 × 10 ∴ D2 = 18 days |
|
| 39. |
There is a need of 8 bottle of water to fill a bucket when capacity of each bottle is 2.25 litres. How many bottles of water will be needed to fill this bucket, if each bottle is of 1.2 liters capacity now?1). 82). 153). 164). 18 |
|
Answer» ? when using 2.25 liter bottle, PER bottle fill 1/8 of BUCKET. ∴ when using 1.2 liter bottle, per bottle fill (1.2/2.25) × 1/8 = 1/15 of the bucket. ∴ By using bottles of capacity 1.2 liters, 15 bottles are required to full the bucket. |
|
| 40. |
A project is done in 30 days by three partners Nikhil, Rohit and Sanjeev. Sanjeev is twice as fast as Rohit and Rohit is thrice as fast as Nikhil. Calculate in how much time will Nikhil alone can complete the project?1). 150 days2). 200 days3). 270 days4). 300 days |
|
Answer» let Nikhil can COMPLETE the project in X DAYS. ∴ Rohit will complete it in x/3 days and Sanjeev will do it in x/6 days. ? In one day Nikhil, Rohit and Sanjeev will complete 1/x, 3/x and 6/x of the project. ∴ combined one day work of all partner = 1/x + 3/x + 6/x = 10/x = 1/30 (given) x = 300 days |
|
| 41. |
Working 5 hours a day, A can complete a piece of work in 8 days and working 6 hours a day B can complete the same work in 10 days. Working 8 hours a day both of them can complete the work in ____.1). 3 days2). 4 days3). 4.5 days4). 5.4 days |
|
Answer» A can complete the WORK in hours = 5 × 8 = 40 hours B can complete the work in hours = 6 × 10 = 60 hours A's 1 HOUR's work = 1/40 B's 1 hour's work = 1/60 (A + B)’s 1 hour's work = (1/40) + (1/60) = 1/24 Both will finish work in 24 DAYS. Number of days of 8 hours a day = 24 × 1/8 = 3 ∴ They require 3 days to complete the work. |
|
| 42. |
1). 252). 243). 164). 19 |
|
Answer» Let, T worked for ‘y’ DAYS. ⇒ R worked for (y - 8) days and S worked for (y - 12) days. R completes the work in 36 days. ⇒ R’s 1 day’s work = 1/36 ⇒ R’s (y - 8) day’s work = (y - 8)/36 S completes the work in 54 days. ⇒ S’s 1 day’s work = 1/54 ⇒ S’s (y - 12) day’s work = (y - 12)/54 T can complete the work in 72 days. ⇒ T’s 1 day’s work = 1/72 ⇒ T’s y day’s work = y/72 According to the QUESTION, ⇒ $(\FRAC{{y - 8}}{{36}} + \frac{{y - 12}}{{54}} + \frac{y}{{72}} = 1 \Rightarrow \frac{{6\left( {y - 8} \right) + 4\left( {y - 12} \right) + 3y}}{{216}} = 1)$ ⇒ 13y - 96 = 216 ⇒ 13y = 312 ⇒ y = 24 days ∴ The number of days for which T worked = 24 days |
|
| 43. |
A cistern that would normally be filled in 6 hours is now taking 4 hours more because of a leak. In how much time, will the leak empty the cistern?1). 12 hours2). 8 hours3). 15 hours4). 9 hours |
|
Answer» Time TAKEN by the inlet PIPE to fill the cistern = 6 hours So, part of cistern filled by inlet pipe in 1 hour = 1/6 Time taken to fill the cistern with leak = 6 hours + 4 hours = 10 hours part of cistern filled by inlet pipe with leak in 1 hour = 1/10 Let the leak take x hours to empty the filled tank. If an inlet pipe can fill the tank in x hours, then the portion filled in 1 hour = 1/x $(\BEGIN{array}{l}\frac{1}{6}\; - \;\frac{1}{x}\; = \frac{1}{{10}}\\ \Rightarrow \;\frac{1}{6}\; - \frac{1}{{10}}\; = \frac{1}{x}\\ \Rightarrow \;\frac{{10\; - \;6}}{{60}}\; = \;\;\frac{1}{x}\\ \Rightarrow \;\frac{4}{{60}}\; = \;\frac{1}{x}\end{array})$ ⇒ 4x = 60 ⇒ x = 15 hours ∴Time taken by leak to empty the cistern = x = 15 hours |
|
| 44. |
Taps A and B can fill a tank full in 3 hours. Tap B alone can fill the empty tank in 2 hours. How long will tap A take to vacate the tank if it is 25% filled. 1). 1.5 hours2). 2 hours3). 2.5 hours4). 3.2 hours |
|
Answer» Let the capacity of the tank = X ltr Time TAKEN by A and B to fill the tank = 3 hr Tank filled by A and B in 1 hr = x/3 Time taken by B to fill the tank = 2 hr Tank filled by B in 1 hr = x/2 Tank filled by A in 1 hr = x/2 - x/3 = x/6 Time taken by A to completely empty the tank = 6 hr Time taken by A empty the 25% (1/4 )tank = 6 × (1/4) = 1.5 hr |
|
| 45. |
1). 2/15 days2). 7/30 days3). 8/17 days4). 10 days |
|
Answer» Mike and Mindy’s 1 day work = 1/6 Mindy and JOSH’s 1 day work = 1/10 Mike, Mindy and Josh’s 1 day work = 1/4 So, Mike and Josh’s 1 day work = 2 × (Mike, Mindy and Josh’s 1 day work) - (Mike and Mindy’s 1 day work) - (Mindy and Josh’s 1 day work) ⇒ 2 × (1/4) - (1/6) - (1/10) ⇒ (1/2) - (4/15) = 7/30 ∴ Time taken by Mike and Josh to complete the PAINTING = 1/(7/30) = 30/7 = $(4\frac{2}{7}{\rm{\;days}})$ |
|
| 46. |
Two pipes together can fill a cistern in 36 hours. If another draining pipe attached to the tank, it takes 9 hours longer to fill the tank. Find in how much time can the drain pipe alone can empty a half full tank.1). 180 hours2). 90 hours3). 315 hours4). Can’t be determined |
||||||||
Answer»
C drains out one UNIT of water in one hour Capacity of the tank = 180 Half the capacity of the tank = 90 ∴ TIME required to EMPTY the half-filled tank = 90/1 = 90 hours |
|||||||||
| 47. |
1). 60/13 days2). 13/60 days3). 19/25 days4). 25/19 days |
|
Answer» Work done by the MAN in 1 DAY = 1/10 Work done by the FATHER in 1 day = 1/15 Work done by the son in 1 day = 1/20 Work done by them together in 1 day = 1/10 + 1/15 + 1/20 = (6 + 4 + 3) /60 = 13/60 Time taken by them to complete the job = 60/13 DAYS |
|
| 48. |
A garrison of 500 men had provisions for 27 days. After 3 days, a reinforcement of 300 men arrived. The remaining food will now last for how many days?1). 152). 163). \(17\frac{1}{2}\)4). 18 |
|
Answer» Total provision (in men days) = 500 × 27 = 13500 After 3 days, provision left (in men days) = 13500 – 3 × 500 = 13500 – 1500 = 12000 Now, total new number of men = 500 + 300 = 800 Hence provision will LAST for = 12000/800 = 15 days |
|
| 49. |
X, Y and Z can do a piece of work in 60, 90 and 180 days respectively. In how many days X can do the work if he is assisted by Y and Z on every third day?1). 452). 153). 754). 60 |
|
Answer» X can complete the work in = 60 days ∴ X’s 1 day’s work = 1/60 Y can complete the work in = 90 days ∴ Y’s 1 day’s work = 1/90 Z can complete the work in = 180 days ∴ Z’s 1 day’s work = 1/180 X completes 1/30 work in 2 days. ∴ (X + Y + Z)’s 3rd day work, ⇒ 1/60 + 1/90 + 1/180 ⇒ 6/180 ⇒ 1/30 (X + Y + Z) can do 1/30 + 1/30 work in 3 days = 1/15 ∴ They can complete the work in = 15 × 3 = 45 days |
|