1). 2 days2). 4 days3). 6 days4). 8 days |
|
Answer» Work done by Imran in ONE day = 1/12 Work done by Hashim in one day = 1/36 Work done by Rajat in one day = 1/18 Work done by Imran and Hashim TOGETHER in one day = (1/12) + (1/36) = 1/9 Work done by Imran and Rajat together in one day = (1/12) + (1/18) = 5/36 Work done in 2 DAYS = (1/9) + (5/36) = 1/4 Time taken to COMPLETE the work = 2/(1/4) = 2×4 = 8 days |
|