96 men can complete a work in 40 days. They all worked for 10 days. But to finish the work before time, contractor brought N more men to work. Because of this, the work got finished in a total of 34 days. What is the value of N?1). 162). 203). 244). 27

Answer»

The total number of man-days will be same in both the cases.

96 × 40 = 96 × 10 + (96 + N) × (34 – 10)

⇒ 3840 = 960 + 2304 + 24N

⇒ N = 576/24 = 24