96 men can complete a work in 40 days. They all worked for 10 days. But to finish the work before time, contractor brought N more men to work. Because of this, the work got finished in a total of 34 days. What is the value of N?1). 162). 203). 244). 27 |
|
Answer» The total number of man-days will be same in both the cases. ⇒ 96 × 40 = 96 × 10 + (96 + N) × (34 – 10) ⇒ 3840 = 960 + 2304 + 24N ⇒ N = 576/24 = 24 |
|