| 1. |
Aman takes thrice as much time as Baman to do a piece work. If they working together the work will be completed in 12 days. Then Baman can do the work alone in1). 24 days2). 48 days3). 16 days4). 28 days |
|
Answer» LET Baman takes X DAYS to complete the work then AMAN will TAKE 3X days to complete it. ∴ 1/X + 1/3X = 1/12 X = 16 days |
|