Working 5 hours a day, A can complete a piece of work in 8 days and working 6 hours a day B can complete the same work in 10 days. Working 8 hours a day both of them can complete the work in ____.1). 3 days2). 4 days3). 4.5 days4). 5.4 days |
|
Answer» A can complete the WORK in hours = 5 × 8 = 40 hours B can complete the work in hours = 6 × 10 = 60 hours A's 1 HOUR's work = 1/40 B's 1 hour's work = 1/60 (A + B)’s 1 hour's work = (1/40) + (1/60) = 1/24 Both will finish work in 24 DAYS. Number of days of 8 hours a day = 24 × 1/8 = 3 ∴ They require 3 days to complete the work. |
|