1.

1). 2/15 days2). 7/30 days3). 8/17 days4). 10 days

Answer»

Mike and Mindy’s 1 day work = 1/6

Mindy and JOSH’s 1 day work = 1/10

Mike, Mindy and Josh’s 1 day work = 1/4

So, Mike and Josh’s 1 day work = 2 × (Mike, Mindy and Josh’s 1 day work) - (Mike and Mindy’s 1 day work) - (Mindy and Josh’s 1 day work)

⇒ 2 × (1/4) - (1/6) - (1/10)

⇒ (1/2) - (4/15) = 7/30

∴ Time taken by Mike and Josh to complete the PAINTING = 1/(7/30) = 30/7 = $(4\frac{2}{7}{\rm{\;days}})$