9 men working for 7 hours a day can complete a piece of work in 20 days, in how many days can 7 men working for 10 hours a day complete the same piece of work?1). 21 days2). 22 days3). 20 day4). 18 days

Answer»

We know that WORK = M × D × H

Here,

M = no. of men

D = no of DAYS

H = hours

So,

M1 × D1 × H1 = M2 × D2 × H2

9 × 20 × 7 = 7 × D2 × 10

∴ D2 = 18 days