A’s 1 day WORK = 1/10

B’s 1 day work = 1/50

Together with C, they did the work in 6.25 days

A’s 1 day work + B’s 1 day work + C’s 1 day work = 1/6.25 = 4/25

⇒ C’s 1 day work = 4/25 - 1/10 - 1/50 = 4/25 - 3/25 = 1/25

∴ C can alone do the JOB in 25 days