| 1. |
1). Rs. 45002). Rs. 30003). Rs. 20004). Rs. 1500 |
|
Answer» ⇒ Work done by RAHUL in 8 DAYS = 8 × (1/16) = 1/2 ⇒ Work done by Ravi in 8 days = 8 × (1/24) = 1/3 It means, Rahul and Ravi done 1/2 and 1/3rd of work, respectively, in 8 days ⇒ Work done by kamlesh = {1 – (1/2 + 1/3)} = 1 – 5/6 = 1/6 ⇒ Rahul’s SHARE: Ravi’s share : Kamlesh's share = 1/2 : 1/3 = 3 : 2 ⇒ Kamlesh’s share = (1/6) × 9,000 = 1500 ∴ Kamlesh’s share is Rs. 1500 |
|