| 1. |
12 men finished 1/4 part of whole work in 6 days. Find the number of additional men required to complete the job in next 6 days.1). 362). 123). 184). 24 |
|
Answer» 12 men finished 1/4 part of whole work in 6 days, ⇒ 12 men finished whole work in 24 days, ⇒ Total work = 12 × 24 = 288 units, LET x ADDITIONAL men are required, REMAINING work = 288 × 3/4 = 216 units ⇒ To finish 216 units work in next 6 days, men required = 216/6 = 36 men ∴ Additional men required are 24. |
|