1.

12 men finished 1/4 part of whole work in 6 days. Find the number of additional men required to complete the job in next 6 days.1). 362). 123). 184). 24

Answer»

12 men finished 1/4 part of whole work in 6 days,

⇒ 12 men finished whole work in 24 days,

⇒ Total work = 12 × 24 = 288 units,

LET x ADDITIONAL men are required,

REMAINING work = 288 × 3/4 = 216 units

⇒ To finish 216 units work in next 6 days, men required = 216/6 = 36 men

∴ Additional men required are 24.