150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped on the second day, four more workers dropped on third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed?1). 282). 243). 254). 30 |
| Answer» OPTION option 3 is the CORRECT ANSWER | |