| 1. |
A and B together can do a piece of work in 12 days which B and C together can do in 16 days. After A has been working at it for 5 days and B for 7 days, C finishes it in 13 days. In how many days B could finish the work ?1). 48 days2). 24 days3). 16 days4). 12 days |
| Answer» 48 DAYS is the CORRECT ANSWER as PER the ssc answer key | |